Friday, April 30, 2010
Final Cut
Step 1: Go through the charges with a fine tooth comb and compare everything they are charging you to the contract. This step yielded about $3,800 worth of disputed items. The largest was an argument over how much the contractor paid for the tub. Colleen sent them a very explicit email stating how much the tub cost both at an online retailer, or if thy weren't comfortable with that, then the price at Lowes. They chose to get the tub elsewhere and overpaid by almost $2000 and passed those 'savings' on to us. Most of the remainder of disputed stuff was for not reducing the amount we owed for items on our allowance sheet which we purchased ourselves (after the tub incident, we preferred to make purchases when possible). Everything from bathroom mirrors to overhead lights added up to quite a bit.
Step 2: Have a meeting. Experience has taught me that you need to have a meeting with all interested parties on your home turf and talk in generalities about what's wrong. If you get too specific at this stage, they will get defensive and try to hone in on one dispute, tell you why you shouldn't be disputing that item, and then assume all the rest of the disputes are wrong because they disagree with that one piece. Colleen and I had a great meeting with our Project Manager and our Architect in our new dining area. They listened attentively, didn't get defensive, and when it was all over, I sent them the detailed workup of every cent I wanted back.
Step 3: Be prepared to bargain. In Step 1, you really want to ask for the moon. That way, they can counteroffer to save face and you still end up getting most of what you wanted in the first place. Fortunately for Colleen and me, the only thing they didn't really go for was some vague he said/she said items that I didn't really think would fly anyway. They gave us pretty much everything I felt we were owed.
Step 4: Pay the invoice. Unfortunately, the approved final invoice ended up coming at pretty much the exact time that Colleen was paying for the second half of the Beach Week trip (we split a house with about 16 friends so paying for half of it is a big check). It also came just before we got our tax refund. Fortunately, we were able to shuffle enough cash around to get everything paid, but never forget the importance of cash flow.
So nearly 11 months to the day after giving them the first payment, we gave them the last. Now for all the stuff Colleen and I have to still do . . .
Sunday, April 11, 2010
Moulding Day
Jeremy showed up to my house first. He brought an air compressor, a nail gun, a saws-all, a miter saw, a Drimmel, and a tool box big enough for a toddler to build a fort inside of. Duncan brought three coping saws, each one smaller than the last. I'm not sure exactly what the smallest one is supposed to be used for, it may have actually been a cheese slicer.

Wednesday, February 10, 2010
Snowpocalypse 2010


The snow was deep . . .



But did I mention it was beautiful?
Monday, February 1, 2010
Getting Out of the House
We started out flying into Geneva where we met up with some college friends of mine and headed to our first major destination: Flaine (pronounced Flin). Flaine is a ski town in the French alps. The snow was good, the scenery was awesome, but the mountain was way too 'natural' for my liking (natural means they don't cut trails, so there are lots of places that are uphill). I nearly killed myself on the last day trying to get some nice pictures, but that's another story. For now, just enjoy the photos.







Thursday, January 14, 2010
Rest for the Weary
First, the bathroom vanity is all done. They finally got the new top in and installed the faucets just a day or two later. It looks really nice. The shower enclosure still isn't done and there are a few towel bars to hang, but this sucker is getting really close to complete.

Our washer and dryer were delivered the weekend before last. The dryer had a piece broken off of the door preventing it from snapping closed, but we were still able to use both and did so a lot. You can say I'm biased because I used to work there, but my whole experience with Sears on the product delivery side has been really great so far (obviously the sales experience was good since I hand-picked my sales person). Also visible to the right is our tankless gas hot water heater.

The next big thing, as the previous blog alluded to, was the floor getting installed. I spent better than 20 hours over two days with help from a cast of thousands. It really was a team effort. Snap in flooring is most easily installed by putting an entire row of boards together, and then snapping that row in all at once. This isn't a big deal if your room is 10 or even 15 feet long. However, when the room is more than 30 feet, it becomes challenging. To help, whenever Paul and I (then later Duncan and I, then even later, Jeremy and I) would finish a row, we would yell "Huddle Up" and anyone who was in the house (sometimes as many as five people) would show up to snap in the row. Unfortunately, toward the late night of Sunday, it was pretty much just me working. This picture is me still working to finish those last few rows (you can see the blue underlayment to the left). [Colleen would like to interject that she was trying to help and took this picture while awaiting her next assignment]
I'm hopeful, though not confident, that the shower enclosure and all the little items left on our 'punch list' will be completed when we get back from our trip. We can't wait to move into the new bedroom! Check back with us in two weeks and we'll find out together (I may have to use this space for some vacation pics too).
Sunday, January 10, 2010
A-wop-bab-a-loo-bop a whop . . .
Thursday, December 24, 2009
Christmas Comes Early
Bedroom:
We had just finished painting the walls of the master bedroom in the last blog entry. Shortly after that at 7:00am on a Saturday, the carpet guys showed up to carpet the bedroom. I won't even get into how unpleasant it is to be unexpectedly interrupted at 7am on a Saturday, because the big problem was that we were planning to paint the trim of the bedroom that day. Colleen, who was also sick, 'greeted' the carpet crew and thoughtfully explained to them that perhaps it would be better if they came back a few days later. They left the rolls of carpet and exited stage left. Five verification calls and three schedule changes later, they showed up again to install the carpet. Below is our new master bedroom and it is done! Well, we need to paint the doors and there is some minor touchup paint work to do, but it is ready to be moved into as soon as the bathroom is done and we don't have the threat of workers walking through our bedroom.
Bathroom:
The bathroom has had a lot of work done to it. The tile was installed and the flooring were both installed a few weeks ago. As I alluded to before though, it's the last 10% that is holding things back. Even though I sent a warning email to our project manager not once, but twice, telling him that the tile guys were going to tile over the access to the tub plumbing and motor, nothing was done. The result was that they had to cut out tiles that we had just paid to have installed. Ultimately they will have to create some kind of access panel to replace those tiles. Early this morning we saw the first attempt at that panel and it was a feeble attempt. I had a conversation with the carpenter and I think we are going to find a better solution to that little issue. Since this is Christmas, this little story has to have a happy ending. In this case, it was that the plumbing was all done! Our early Christmas present was getting to try out the tub last night. I have to say, it was pretty awesome. Our tankless hot water heater definitely did the trick and the inline water heater in the tub (it heats the water as it recirculates in the jets) is fantastic.
There are a few other things around the bathroom that still need some work. Our bathroom counter was ordered with the faucet holes in the wrong place, so that still needs to be replaced and the faucets installed. The shower enclosure needs to be done as well. The contractor for that spent all of last week and most of this week not returning our calls, so that is still in the very early stages of what will likely be a few weeks long process..
Greatroom:
Not much happened in the greatroom for a long time, largely because the contractors are done with that room and Colleen and I have been trying to get paint done elsewhere. Finally, Colleen got to lay down the first coat of paint in the greatroom only hours ago. We are hoping to get the walls painted over Christmas, the trim over New Years, and the floor in the weekend after that. The goal is to have the room ready for entertaining in time for our Super Bowl party. That would be a pretty simple task except for the fact that Colleen and I are headed to Europe for two weeks. Such a tough life . . .
Monday, December 7, 2009
And it was Good

We have also been able to gather the waters under heaven in one place. By which of course I mean the sink now works. Somewhat less miraculous than God's third day on the job, but an accomplishment none the less.
p.s. Happy 5 month anniversary to the Addition!
Sunday, December 6, 2009
Ups and Downs
and microhood have been here for months. We were really hoping that we would be able to get the plumber out here to install the faucets and the stove. Well, he did . . . sort of. The stove and dishwasher are sitting in their spots and the sink faucet was installed, but he didn't leave himself enough time to get into the crawl space to hook up the drain or the gas line, so none of it actually works yet. So close! This was especially unfortunate with the party this weekend. We put some flower arrangements in the nonworking sink to keep people from using it so at least it looked pretty.



Sunday, November 29, 2009
Paint by Numbers (Painting: Day 4)
Gallons of paint: 14
Square feet painted: 6160 (440 sq ft per gallon); 0.14 acres
.


Saturday, November 28, 2009
Painting: Day 3
Colleen's dad took the day off from painting to hunt. To fill in for him, we brought in my mom. We got quite a few pictures of her today, but none of her face. I think that's because she spent almost every minute here facing a wall putting down tape or paint. That's her on the right (guess from which side of my family I got my height).

Our electrician was here working hard for at least 8 or 9 hours and still didn't get everything done. Again though, there are some highlights: the kitchen and master bedroom are completely wired (including our awesome new ceiling fan); elsewhere all of the switches and outlets are in, but few of the lights have been installed. The lights that are installed look pretty sweet. Hopefully our electrician will be back again soon to finish up.
Friday, November 27, 2009
Painting: Day 2
So far we're doing okay on our goals. We have at least one coat of paint on all the surfaces that lights will be installed on. The kitchen, bedroom, and bathroom ceilings are done, and we hope to have the bathroom wall and one or two of the closet ceilings done by the time the lights are installed tomorrow. See some highlights of the fun below.
Thursday, November 26, 2009
Count(er)ing Our Blessings
It took them about 3 hours to install and they look great (again, please ignore the floor). 

We've spent much of the last two evenings shelf papering and putting dishes in our new cabinets. It's extremely satisfying to finally be reversing the flow of stuff by taking it out of storage and putting it into the kitchen. We are doing lots more painting over the holiday weekend and quite a few things are slated for next week. We should get our appliances and sink faucets installed. I'm hopeful the thermostat will finally be installed so we can get some heat in the addition. Also, our tile is due to be 'produced' on Monday so it might arrive before the end of next week.
Saturday, November 21, 2009
Optimal Prime
Just because we are painting, don't think the addition is done, it is just to the point where painting needs to happen so that other things can happen. In the case of the kitchen, the counters are due to be delivered soon (about a 50/50 chance of having them here before Thanksgiving). The bedroom ceiling has to be done so they can install our light fixture so that we can get our plugs and switches installed (so that we can do more painting).
On a general note, it is not often that things go more or less right for a few weeks in a row, but we are definitely on a good streak recently. My November 7th post made some bold predictions about things that I hoped would get done, and nearly all of them are done or on schedule: The cabinets are in; the countertops were measured last Monday and due in soon; the grading was done despite the heat pump; the vast majority of the trim has been finished; and Colleen and I are in fact painting. Hopefully that momentum can continue for a few more weeks. Lots of important stuff is due in soon.

Thursday, November 12, 2009
Cabinets!



Saturday, November 7, 2009
Happy 4 Month Birthday
Monday, November 2, 2009
Glimpsing the Future
Wednesday, October 28, 2009
Days of Rain Without Leaks: 1
While Bruce slept soundly Monday night, I was awakened by heavy rain. After a long consultation with the angel on my left shoulder and the devil on my right, I dragged myself up to see where we needed buckets THIS time. [I know those of you with kids are already thinking this is NOT newsworthy.] I spent about ten minutes with a flashlight upstairs and downstairs checking ceilings, walls, closets, outlets, and light switches, all of which have previously had water dripping/pouring out of them. The only dampness I found was a couple of slightly dark spots in the ceiling that I was almost certain had been freshly spackled that day and just hadn't fully dried.
I crawled back in bed and eventually stopped thinking about the wet spots and the beads of water that could be forming at that very minute. When we got up in the morning (and I explained to Bruce why on earth I was on my tiptoes poking at the ceiling in my pajamas), the dark spots were either smaller or gone. And after a full day of rain yesterday, our buckets remain dry!
Monday, October 26, 2009
Something's Done! (almost)
Saturday, October 24, 2009
Party Time?
If the weather holds out and the retaining wall really is all done on Sunday, the final grade should happen early next week. The goal was then to get the heat pump in and running pre-party. While that is still a possibility, I would no longer call it likely since there would be at most four days to build a base for it, have it delivered, installed, and working correctly.
Fortunately, cleanliness and heat are not two things that are required for a successful B and B Party as previous years have clearly demonstrated. Still, when I look at the room pictured below my first thought is not: Let's Party!